NASA accomplished the Decommissioning Project's signature achievement to date in February 2005, with the completion of all reactor segmentation activity. During the 18 months of segmentation work, NASA removed all the internal components of the reactor tank, including the core box, then cut the tank into pieces, packaging and sending the pieces to the Envirocare licensed disposal facility in Utah .
To view larger images click on the thumbnail images.
NASA reached another project milestone with the removal of virtually all fixed equipment from Reactor Facility buildings and structures. In 2005 NASA removed, packaged and shipped more than four million pounds of fixed equipment (and more than eight million for the project), including wires, electrical panels, lights, pipes, pumps, valves, stairs, racks, doors and railings. Work was done in the Containment Vessel and both the Hot and Cold Retention Areas, which contained tanks used for holding water contaminated from reactor activities when the facility was operational.
Below is a series of five photos related to the containment vessel annulus. |
||
The two photosto the right are "before" and "after" photos. The left-most photo shows fixed equipment removal in the Containment Vessel annulus, including piping, racks and a railing, all adjacent to the building wall. The right-most photo shows the bare wall, once all equipment was removed. |
||
During the spring and summer, NASA excavated, packaged and shipped 10 million pounds of soil that had been lightly contaminated during reactor operations. NASA removed the soil and placed it in special fabric bags that had a capacity of 15,000 pounds each. In order to ensure safety, NASA used a capacity of just 5,000 pounds each. All of the bags were numbered and weighed, then placed in containers known as “Super Sacks” for shipment by truck to a rail yard in Willard and then by train to Envirocare. NASA continually monitored the remaining soil to ensure that it met project cleanup standards.
Early in 2005, NASA began work on the decontamination of embedded piping systems – pipes covered in concrete and located from three feet to 30 feet below grade in Reactor Facility buildings (see article on page one). NASA stopped work in February to evaluate better approaches to decontamination and test out several techniques, all of which proved effective. NASA is currently undertaking decontamination work on embedded piping in the Primary Process Piping Room, at the minus-25-foot level of the Reactor Building . This room was a central hub for several piping systems when the reactor was operational.
| Below is a series of three photos on the decontamination of embedded piping. |
|
| In the photo to the left, a worker is shown with a probe, at the center of photo, used to remove mud and dirt from embedded piping during early survey work. | |
| At the photo to the right, workers are shown using a probe equipped with a video camera and a radiation monitor to survey embedded piping for contamination. At the bottom of the photo they are shown examining the probe and looking into a video monitor (at the center of the photo). | |
Last summer, NASA conducted what was termed “proof of process,” during which it tested a variety of decontamination techniques – all of which proved successful. The photo to the right shows a yellow pumping machine for a high-powered vacuum machine, one of the techniques employed. |
|
![]()
Best viewed with Internet Explorer 5.0 or higher with 1024 X 768 display setting
Responsible NASA Official: Keith Peecook {keith.m.peecook@nasa.gov}
Web Administrator: Sandra Jacobson, SAIC {sandra.jacobson@grc.nasa.gov}
NASA Glenn Research Center External Website | Accessibility | Privacy Policy and Important Notices
Last update:
February 2008